14 men can finish a piece of work in 26 days how many men will be needed to finish it in 16 days​

Answers

Answered by RvChaudharY50
25

Answer:

M1 * D1 = M2 * D2

14 * 26 = X * 16

X = 14*26/16 = 22.75 men (Ans)

(Question is misprint)