14 men can finish a work in 30 days. How many days will it take to finish the work if its done by 12 men?
Answers
Answered by
2
Answer:
35days
Step-by-step explanation:
Men = 14 , 12
Days = 30 , x
Men : Days = 14 : 30 : : 12 : x
( decrease in men gives increase in days)
14/12 = x/30
14 × 30 = 12 × x
420 = 12x
x = 420 / 12
x = 35
Therefore 12 men can complete work in 35 days
Answered by
3
Step-by-step explanation:
time taken by 14 men to finish the work = 30 days
work done by 14 men in 30 days = 1
work done by 14 men in 1 day = 1/30
work done by 1 man in 1 day = (1/30)*1/14
= 1/420
so, the work done by 12 men in 1 day = (1/420)*12
= 12/420 = 3/105 = 1/35
so time taken by 12 men to finish the work
== 35 days ANSWER.
I hope it will help you