Math, asked by anaskhan2498, 3 months ago

14 persons working 5 hours daily can complete one third of
the work in 8 days. How many hours per day are needed to
complete the rest of work in 4 days by 35 persons?​

Answers

Answered by dsanapaw
1

Answer:

P can complete a work in 12 days working 8 hours a day. ... = 96 hrs. Q can complete the work in (8 x 10) hrs. = 80 hrs.

Step-by-step explanation:

Answered by amanraj56
1

Step-by-step explanation:

(M1×D1×H1)/W1=(M2×D2×H2)/W2

(14×8×5)1/3=(35×4×X)/(1-1/3)

560/(1/3)= 140X/(2/3)

560= 140X/2

560= 70X

8=X

hence no. of hours is 8