14 women can do a piece of work in 48 days if 6 of the women deny to work the how many days are reqired to complete the work
Answers
Answered by
0
Answer:
84 is the answer
Step-by-step explanation:
14 women does the work in 48 days ,
therefore 1woman will do the work in 14*48 days,
And,(14-6)women will do the work in 14*48/(14-6)
=14*48/8=14*6=84 days