142. Twenty five workers were employed to complete
a compound wall in 12 days. Five workers left
after working for 4 days. The remaining 20
workers completed the work. In how many
days the total job was completed?
(a) 15 days
(b) 16 days
(c) 14 days
(d) 18 days.
143. In a garden there are 8 rows and 10 columne
Answers
14 Days.
If 1 worker was to make the wall then he would take 25×12 days. So 300 Days.
25 workers worked for 4 days. They did the same work which a single worker would have done in 100 days. So 200 Days of work is left. 20 workers would do the work in 200/20 days= 10 days. So total days =10+4=14 days.
Given :
Twenty five workers were employed to complete a compound wall in 12 days. Five workers left after working for 4 days. The remaining 20 workers completed the work.
To Find:
In how many days the total job was completed?
Solution:
25 workers completed work in days = 12
25 workers 1 day work =
25 workers 4 days work =
Remaining work =
25 workers complete work in days = 12
1 worker complete work in days =
20 workers complete work in days =
20 workers completework in days =
No. of days required to complete work = 10+4=14 days
Hence the total job was completed in 14 days