15 men and 6 women or 9 men and 8 women are required to complete a task in 25 days. If the work is to be completed in 15 days and the number of men is 19, how many women will be required? please give soln​

Answers

Answered by arnavmaurya07m
0

10 and 12 women's are required

I hope it helps you