15 men can do a piece of work in 80 days . How long will it take to finish the work if 5 men are added

Answers

Answered by Serah24
9

Answer:

60 days

Explanation:

15 × 80 = 1200

then 5 men were added

:. 1200/15+5

:. 1200/20 = 60

:. 60 days