150 workers were engaged to finish a piece of work in a certain number of days. 4 worker dropped the second day, four more workers dropped the third day and soon. it took 8 more days than expected to finish the work now. find the number of days in which the work was completed
Answers
Answered by
3
Let x be the number of days in which 150 workers finish the work.
According to the given information,
150x = 150 + 146 + 142 + …. (x + 8) terms
The series 150 + 146 + 142 + …. (x + 8) terms is an A.P. with first term 146, common difference –4 and number of terms as (x + 8)
However, x cannot be negative.
∴x = 17
Therefore, originally, the number of days in which the work was completed is 17.
Thus, required number of days = (17 + 8) = 25
According to the given information,
150x = 150 + 146 + 142 + …. (x + 8) terms
The series 150 + 146 + 142 + …. (x + 8) terms is an A.P. with first term 146, common difference –4 and number of terms as (x + 8)
However, x cannot be negative.
∴x = 17
Therefore, originally, the number of days in which the work was completed is 17.
Thus, required number of days = (17 + 8) = 25