150 workers were engaged to finish a work in a certain number of days for workers dropped on the 2nd day and 4 more workers dropped on the third day and so on it takes 8 more days to finish the work now find the number of days in which the workers have concluded
Answers
Answered by
7
Sol: Suppose the work is completed in n days.
Since 4 workers went away on every day except the first day.
∴ Total number of worker who worked all the n days is the sum of n terms of A.P. with first term 150 and common difference – 4.
Total number of worker who worked all the n days = n/2[2 x 150 + (n-1) x -4 ] = n (152 – 2n)
If the workers would not have went away, then the work would have finished in (n – 8) days with 150 workers working on every day.
∴ Total number of workers who would have worked all n days = 150 (n – 8)
∴ n (152 – 2n) = 150 (n – 8) ⇒ 152n – 2n2 = 150n – 1200 ⇒ 2n2 – 2n – 1200 = 0
⇒ n2 – n – 600 = 0 ⇒ n2 – 25n + 24n – 600 = 0 ⇒ n(n – 25) + 24 (n + 25) = 0
⇒ (n – 25) (n + 24) = 0 ⇒ n – 25 = 0 or n + 24 = 0 ⇒ n = 25 or n = – 24
⇒ n = 25 ( Number of days cannot be negative)
Thus, the work is completed in 25 days.
Since 4 workers went away on every day except the first day.
∴ Total number of worker who worked all the n days is the sum of n terms of A.P. with first term 150 and common difference – 4.
Total number of worker who worked all the n days = n/2[2 x 150 + (n-1) x -4 ] = n (152 – 2n)
If the workers would not have went away, then the work would have finished in (n – 8) days with 150 workers working on every day.
∴ Total number of workers who would have worked all n days = 150 (n – 8)
∴ n (152 – 2n) = 150 (n – 8) ⇒ 152n – 2n2 = 150n – 1200 ⇒ 2n2 – 2n – 1200 = 0
⇒ n2 – n – 600 = 0 ⇒ n2 – 25n + 24n – 600 = 0 ⇒ n(n – 25) + 24 (n + 25) = 0
⇒ (n – 25) (n + 24) = 0 ⇒ n – 25 = 0 or n + 24 = 0 ⇒ n = 25 or n = – 24
⇒ n = 25 ( Number of days cannot be negative)
Thus, the work is completed in 25 days.
Cutiepie93:
hope it helps you
Similar questions