Math, asked by ItzPriya665, 6 months ago


16. An object of mass, m is moving with a constant velocity, v. How much work should

be done on the object in order to bring the object to rest​

Answers

Answered by ItsBrainest
2

Step-by-step explanation:

how much work should be done on the object in order to bring the object to rest? To bring the object to rest, 1/2 mv^2amount of work is required to be done on the object.

Answered by Anonymous
6

Ans. In order to bring the object to rest the work done must be equal to the kinetic energy of the moving object