Math, asked by sahilvirdi08, 1 month ago

16 Men are able to complete a piece of work in 12 days working 14 hours a day. How long will 28 med, working 12 hours a day take to complete the work​

Answers

Answered by yenikapatisuribabu
1

Answer:

men working hours days

16 14. 12

28 12 X

28×12×X=16×14×12

X=(16×14×12)÷(28×12)

X=2688÷336

X=8 days

Answered by studentbhalla
0
8days is the correct answer