16 men con Finish a piece of work in
12 days To Finish the 1/4 part of
the work in 4 days. how many men
be required
Answers
Answered by
0
Answer:
let's start it!
Step-by-step explanation:
Days left 12-4=8
work left 1-1/4=3/4
=0.75
1 job can be done by 16 men
0.75 job can be done by 16×0.75 men
=12 men
16 men can do 1 work in 12 days
1 men can do 1 work in 12×16 days
1 men can do 0.75 work in 12×16×0.75 days
12 men can do 0.75 work in 12×16×0.75/12 days
=12 days
men needed 12
days needed 12