16 workers can repair the road of 12 kilometres in 10 days in how many days can 10 workers repair the road 15 kilometres
Answers
Answered by
8
Dear Student,
● Answer -
20 days
◆ Explanation -
Let x be no of days required for 10 workers to repair the road 15 kilometres.
Then,
16 × 10 / 12 = 10 × x / 15
x = (16 × 10 × 15) / (12 × 10)
x = 20 days
Hence, 10 workers can repair the road 15 kilometres in 20 days.
Thanks dear. Hope this is helpful to you...