Math, asked by durgaprasannaturangi, 11 months ago

16 workers can repair the road of 12 kilometres in 10 days in how many days can 10 workers repair the road 15 kilometres ​

Answers

Answered by gadakhsanket
8

Dear Student,

● Answer -

20 days

◆ Explanation -

Let x be no of days required for 10 workers to repair the road 15 kilometres.

Then,

16 × 10 / 12 = 10 × x / 15

x = (16 × 10 × 15) / (12 × 10)

x = 20 days

Hence, 10 workers can repair the road 15 kilometres in 20 days.

Thanks dear. Hope this is helpful to you...