Math, asked by manjotg820, 7 months ago

160 men can build a factory in 32 months. how many months will 256 men to build it under same working conditions.​

Answers

Answered by goodboy2173
0

Answer:

it will take 20 months

Step-by-step explanation:

Calculate the number months for given men

160× 32 = 5120

Now, Calculate the number months for 256 men

5120/256 = 20 months

HOPE YOU UNDERSTAND !!

Answered by rjsingh041993
0

Answer:

20 months will 256 men to build the factory

Step-by-step explanation:

no. of men=160

no. of months = 32

calculate no. of month and men

no. of men×no. of months

160 ×32 = 5120

Now' calculate the no. of month for 256 men

5120\ 256 = 20

I hope this question will may help you