17. Abuilding can be completed in 5 months with 400 workers. However the contractor employed only
250 workers, how many months will he take to complete the building?
Answers
Answered by
2
Answer:
400->5
1->400×5
1->2000
250->2000/250
250->8months
Answered by
5
Answer:
8
Step-by-step explanation:
let
month = x
month. : worker
5: x : 400:250
x/5. = 400/250
x = 1.6*5
x = 8