17 men finish of work in 12 days how many days will be taken by 7 men to finish the same work​

Answers

Answered by scientist88
0

Answer:

17 MEN = 12 DAYS

1 MEN= 12/17

7 MEN = 12/17*7

Step-by-step explanation:

DO THE MULTIPLICATION AT YOUR OWN