17. Which of the following is NOT an input to project plan execution?
A Work authorization system
B. Project plan
C. Corrective action
D. Preventive action
Answers
Answered by
0
Answer:
a) work authorization system
Explanation:
Answered by
0
A Work Authorization System is NOT an input to project plan execution.
Explanation for the answer:
- A work authorization system is a method which is used in conjunction with project management.
- This system is used by the project manager and his or her designees to approve all project work during the course of the current working project management venture.
- Work authorisation systems are not inputs to the project execution plan.
- Hence, the correct answer among all the options is option A. Work authorization system.