175 men can dig a canal 3150 meters long in 36 days how many men are required to dig a canal 3900 meters long in 24 days
Attachments:
![](https://hi-static.z-dn.net/files/d9c/dd69432e9ba4bc4f401f7272928658ac.jpg)
Answers
Answered by
20
3150m Canal in 36 Days = 175 men
1m Canal in 1 day = (175*36)/ 3150 men = 2 men
3900m Canal in 24 days = (2*3900)/ 24 = 325 men
1m Canal in 1 day = (175*36)/ 3150 men = 2 men
3900m Canal in 24 days = (2*3900)/ 24 = 325 men