175 men can dig a canal 3150m long in 36 days how many men are required to dig a canal 3900m long in 24days
Answers
Answered by
8
Answer:
let men in second situation be x
175 men*36 days=3150 m
x men*24 days=3900m
cross multiply
175*36*3900 = x*24*3150
24570000 = 75600x
x = 24570000/75600
x = 325