Math, asked by pallavimahale4840, 10 months ago

18 labour can construct a road in 15 days.how many laboures are needed to complete the same road in 10 days

Answers

Answered by SakshamNigam12
9

Step-by-step explanation:

In inverse variation

18 15

x. 10

x*10=18*15

x=18*15/10

x=27 labours