18 men can finishe a piece of work in 50 days in how many days will 15 men finish it​

Answers

Answered by arsalan88
0

Answer:

Paranormal Antonio even Jul

Answered by finefox20
1

Answer:

60 DAYS

Step-by-step explanation:

18 men do that work in 50 days So 1 men will do in 18 ×

50 = 900 15 men will do in 900÷15= 60