18 women work 9 hours per day to complete 30% of the work in 30 day.The rest work is done by 9 women,working 9 hour per day.Then work did in how many days​

Answers

Answered by Anonymous
4

Given,

30% can be completed by 18 women working about 9 hours

then 100 % work can be completed in .

30*100/30=100 days

70% of work need to be done by 9 women about 9 hours...

18 women complete 30% work in 30 day working for 9 hours..

then,.

9 women can complete the 15% work in 30day days working for 9 hours..

15%work is complete in 30 days

then 70% work can be completed in

70*30/15

=140 days