18 workers Kisi Kam ko 24 din me karte hai to 12 workers isi Kam ko kitne din me Pura karenge
Answers
Answered by
1
if 18 worker's can do a piece of work in 24 days
then 12 worker's can do a piece of work in 'x' days
therefore x=24×12÷18
x=16
therefore 12 worker's can do a piece of work in 16 days..
hope it helps...!
then 12 worker's can do a piece of work in 'x' days
therefore x=24×12÷18
x=16
therefore 12 worker's can do a piece of work in 16 days..
hope it helps...!
santoshkumar42:
answer :32
Answered by
2
18 workers complete their work in =24day
1 worker complete their work work in
=18×24 =432days
12 worker complete their work in
=432/12=36days
I hope it is helpful to you