Math, asked by myiesha, 1 year ago

2/5 of a job Is finished in 30 days. In how many days will be the remaining part of the job be finished?

Answers

Answered by ferozemulani
5

Step-by-step explanation:

remaining job= (1-2/5) = (3/5 ) will be finished in

30*(3/5)/(2/5) = 45 days

Answered by ahmedzynova
4

2/5 of a job is finished in 30 days. In how many days will be the remaining part of the job be finished

______________________________________________________________________

SOLUTION: 2/5 of job is finished in 30 days

Total work will be finished in

30*5/2=75 days

45 days remaining to finish the

remaining work.

THANKS

Similar questions