2/5 of a job Is finished in 30 days. In how many days will be the remaining part of the job be finished?
Answers
Answered by
5
Step-by-step explanation:
remaining job= (1-2/5) = (3/5 ) will be finished in
30*(3/5)/(2/5) = 45 days
Answered by
4
2/5 of a job is finished in 30 days. In how many days will be the remaining part of the job be finished
______________________________________________________________________
SOLUTION: 2/5 of job is finished in 30 days
Total work will be finished in
30*5/2=75 days
45 days remaining to finish the
remaining work.
THANKS