Math, asked by bhartipatil8102, 3 months ago

2 7 If s Labour's completed a work in a fram within 12 days then How many days will it take 6 labours to complete the sume work?​

Answers

Answered by filista75
0

Answer:

1st part

We have,

Worker W

1

=5

Weed a field in days=D

1

=12days

If,

Take worker W

2

=6

Then, Days D

2

=?

Then, we know that,

W

1

D

1

=W

2

D

2

5×12=6×D

2

D

2

=

6

5×12

D

2

=10days

2nd Part,

If workerW

3

=15

Then,

Days D

2

=?

Then, we know that,

W

1

D

1

=W

3

D

3

5×12=15×D

3

D

3

=

15

5×12

D

3

=4days

Hence, this is the answer

Answered by mathwallhabikramda
0

Answer:

4 days

Step-by-step explanation:

4days

Hence, this is the answer.

Attachments: