2. A can do a job in 15 days, and B in 10 days. How many days will they take to finish the job
if they work together?
Answers
Answered by
7
Answer:
☆A's 1 day's work =
♡B's 1 day's work =
♧(A + B)'s 1 day's work =
♤ANSWER = 6 days.
Answered by
2
Answer:
6 days
Step-by-step explanation:
1/15+1/10=2+3/30
=5/30
1/6
here they will finish the work in 6 days