Math, asked by pabila, 11 months ago

2. If 18 men can do a work in 20
days, then 24 men can do this
work in (days)​

Answers

Answered by ami2320
0

One man can do the work in 15 days

Answered by dhanasekartool
0

Answer:

15 days

Step-by-step explanation:

18 * 20 = 24 * x

360 = 24 * x

x = 360 / 24

x = 15 days