2)lf 3 persons can do a piece of work in 8 days, then 4 persons can do it in -
-----days
a)3
b) 6
c) 9
d)8​

Answers

Answered by Anubhwab
0

Answer:

b)6 days

Step-by-step explanation:

Answer: 4 Men can with same ability complete the same work in 6 Days

3 Men can complete the job in 8 Days. So, 4 Men will complete the same job in less number of days

Hence, 4 Men can with same ability complete the same work in (3/4) x 8 = 6 Days.