2 men and 5 women can do a piece of work in 4 days, while one man and one woman
can finish it in 12 days. How long would it take for 1 man to do the work?
cortain distance at
a uniform sneed
need If
the
Answers
Answered by
1
Answer:
please mark me as brainliest
Step-by-step explanation:
let work done by man be M and work done by woman be N
2m+5n=1/4
8m+10n=1
10n=1-8m/10.........(i)
m+n=1/12
12m+12n=1.........(ii)
from (i)
12m+12n=1
12m+12(1-8m/10)=1
implifying you get m=1/12
one man finish works in 12 days