2 men and 7 boys can finish a piece of work in 4 days while 4 men and 4 boys can finish it in 3 days. Find the time taken by one man alone and that by one boy alone.
Answers
Answered by
4
Answer:
Time taken by one man is 15 days.
Time taken by one boy is 60 days.