2 men can complete a piece of work in 14 days. 2 women can complete the same piece of work in 24 days. In how many days will 7 men and 10 women together complete the same piece of work? ​

Answers

Answered by rishismath2020
1

Given:

2m + 7w = 14 days

3m + 8w = 11 days

Formula used:

Total work = Efficiency × days 

Calculations:

⇒ (2m + 7w)14 = (3m + 8w)11

⇒ 28m + 98w = 33m + 88w

⇒ 10w = 5m

⇒ m/w = 2/1

⇒ Total work = (2 × 2 + 7 × 1) × 14

⇒ Total work = 11 × 14

Time taken by 5m and 4 w = (11 × 14)/(5 × 2 + 4 × 1)

⇒ 11 days

∴ Time taken by 5 man and 4 woman is 11 days