2 men can do a piece of work in 10 days how many men are needed to complete the work in 5 days
Answers
Answered by
2
4 men are needed.
Hope it helps u
please mark as brainliest
Answered by
2
To complete in 10 days
number of workers needed is 2
to complete in 1 day worker needed 2×10=20 n
worker
and to complete in 5 days ...
number of workers needed = 20 / 5 = 4 workers .....
heya mate ...hope the answer is helpful....
mark as brain list...✔️✔️