2 women and 5 men can together finish an embroidery work in 4 days while 3 women and 6 men can finish it in 3 days find the taken by 1 women alone to finish the work. and also taken by 1 men alone ?
Answers
Answered by
0
Answer:
m=2 days
w=6 days
Step-by-step explanation:
5m+2w=4
6m+3w=3
15m+6w=12
12m+6w=6
m=2
w=6
Answered by
3
Answer:
Number of days taken by a woman = 18
Number of days taken by a man = 36
Step-by-step explanation:
Let the number of days taken by a woman and a man be x and y.
⇒ 4(2/x + 5/y) = 1
⇒ 2/x + 5/y = 1/4
⇒ 3(3/x + 6/y) = 1
⇒ 3/x + 6/y = 1/3
Putting 1/x = p and 1/y = q in these equations,
we get ⇒ 2p + 5q = 1/4
By cross multiplication, we get
⇒ p/-20 – (-18) = q/-9 – (-18)
= 1/144b- 180 ⇒ p/-2
= q/-1 = 1/-36 ⇒ p/-2
= – 1/36 and q/-1 = 1/-36
⇒ p = 1/18 and q = 1/36
⇒ p = 1/x = 1/18 and q = 1/y = 1/36
⇒ x = 18 and y = 36
Number of days taken by a woman = 18
Number of days taken by a man = 36
hope it helps
Similar questions
Geography,
3 months ago
Geography,
3 months ago
World Languages,
3 months ago
English,
7 months ago
Hindi,
7 months ago
Political Science,
1 year ago
Math,
1 year ago