20 boys are required to complete a work in 100 days. How many boys are required to complete that work in 5 days?
a) 200
b) 250
c) 300
d) 400
Answers
Answered by
2
Answer:
Let the number of boys be x.
x = (100 × 20)/5
400 boys are required to complete that work in 5 days
meslinsmile:
ok
Answered by
2
100 days × 20 boys = 5 days × X boys
100×20 = 5 × X boys
2000 = 5 × X boys
X boys = 2000 / 5
X boys = 400
Ans 400 boys