Math, asked by anime0934609, 14 hours ago

20 men can complete a piece of work in 24days how many men should be left the so that it would complete in 32 days

Answers

Answered by mvinayak2008
1

Answer:

15 worker

Step-by-step explanation:

First we will calculate the work done by one person

=20/24=0.83(approximately)

Total work done by them=0.83*20*24=398.4

work=work

20*24*0.83=0.83*32*x

=398.4=26.56x

x=398.4/26.56=15 workers