20 men can do a piece of work in 15 days. if it is to be completed in 10 days how many more men are necessary

Answers

Answered by nikolatesla2
1
hope it satisfy you
Attachments:

Kushall: x=men not days so it's mean 30 men required OK got it thanks and 30-20=10 men more necessary