- 20 men can finish a piece of work in 30 days. After
how many days should 5 men leave the work so that
it is finished in 35 days?
Answers
Answered by
1
Answer:
15 days
Step-by-step explanation:
20*30=600 units of work
After leave the 5 workers , we have 35 days for complete the work.
In 35 days only 15 workers will do the work.
So the work completed in 35 days by 15 workers = 35 ×15 =525 units
Remaining unit = 600 -525 =75 units
This units would done by 5 workers in ( 75/5) = 15 days
So after 15 days 5 workers should leave the job.