20 men can finish a piece of work in 30 .if 5 more men join them in how many days will they finish the same piece of work?​

Answers

Answered by samy456
1

Correct Question

20 men can complete a piece of work in 25 days. They started the work, and after 5 days, 5 more men joined them. How many days will the work be completed?

Answer

  • The work can be done in =20 x 25 =500 man-days.
  • In 5- days (5 x 20) = 100 man- days of work was done.
  • The remaining (500–100)= 400- man-days of work will be done by (20+ 5)= 25- men in = 400/25= 16- days.
  • So totally the work will be completed in = (5+16)= 21- days.
Answered by agnishasumellikalove
2

 \huge{ \bold{Question:}}

20 men can finish a piece of work in 30 .if 5 more men join them in how many days will they finish the same piece of work?

 \huge{ \bold{Answer:}}

{ \bold{20  \: men \:  can  \: finish  \: the \:  piece \:  of \:  work  \: in  \: 30  \: days.}} \\ { \bold{1  \: men \:  can  \: finish  \: the \:  piece \:  of \:  work  \: in  \: 30 \times 20  \: days.}} \\ { \bold{25  \: men \:  can  \: finish  \: the \:  piece \:  of \:  work  \: in  \:  \frac{30 \times 20}{25}   \: days.}} \\  { \bold{24 \: days}}