20 men can finish a piece of work in 35 days. How many days will be taken by 28 men to finish it.
Answers
Answered by
0
Answer:
25 days
Step-by-step explanation:
20 men- 35 days
1 man-35*20 days
28 men- 35*20/28
Answer-25 days
Answered by
0
The more will be the men, the lesser time it will take to complete the work.
Which means, more men, less time and less men, more time.
So there is inverse relationship between men and time taken by them.
Let the time taken by 28 men be x days
20 men take 35 days
28 men take x days (assumption)
By the problem, 20/28=x/35(inverse relation)
Therefore,x=(20*35)/28
Hence we get,x=25
So the time taken by 28 men to finish the work is 25 days.
Which means, more men, less time and less men, more time.
So there is inverse relationship between men and time taken by them.
Let the time taken by 28 men be x days
20 men take 35 days
28 men take x days (assumption)
By the problem, 20/28=x/35(inverse relation)
Therefore,x=(20*35)/28
Hence we get,x=25
So the time taken by 28 men to finish the work is 25 days.
Similar questions
Political Science,
2 months ago
Computer Science,
2 months ago
History,
2 months ago
Math,
4 months ago
Chemistry,
4 months ago
Biology,
10 months ago
Economy,
10 months ago
Chemistry,
10 months ago