Math, asked by kunalsingh74034, 10 months ago

20 men can reap a field in 30 days how many men must be engaged to reap the same field in 24 days
If you give me a perfect answer I will Mark you as brainlist ​

Answers

Answered by Vipulvm
0

Answer:

16 people must be engaged to complete work in 24 days


Vipulvm: plzz mark it as brainliest
Answered by pranav3954
1

Answer:

total men reap field in 30 days = 20

total men reap field in 1 day = 20 ÷30

total men reap field in 24 days =

20÷30×24 = 16 men

Similar questions