20 men complete a work in 25 days. How many can complete the same work in 10 days?
Answers
Answered by
0
Answer:
20--------25
x----------10
=20*25=500
then, 500/10=50
therefore 50 men will complete same work in 10 days.
Answered by
1
Answer:
⇒ 50 men
Step-by-step explanation:
20 men ⇒ 25 days
Lets determine how days it will take one man first
1 man ⇒ 20 × 25
⇒ 500 days
For 10 days, 500/10
⇒ 50 men
Hope this helps my friend.