Math, asked by singhsaket079, 5 months ago

20 men or 25 boys can do a job in 24 days. In how much days can 16 men and 10 boys do the whole work?​

Answers

Answered by inamdarmisba112
1

Step-by-step explanation:

if number of days at work is same

so we can equate directly

20 men = 25 boys

4 men = 5 boys

1 boy = 4/5 men

10 boys = 4/5 * 10 men

10 boys = 8 men

as 20 men completed work in 24 days

1 mam completes a work in = 24*20 = 480 days

16 men + 10 boys = ?

16 men + 8 men = 24 men

work = 24* 20 / 24 = 20 days

thus, 16 men and 10 boys do the whole work in 20 days