Math, asked by Santoshagarwal, 2 months ago

20 men takes 52 days to build a wall. How many more men are required to build a wall, triple in size, in 60 days?
it's Answer is 32 men
it's urgent​

Answers

Answered by lochansahu16
4

Step-by-step explanation:

Let the work = w

thefore,

in first condition m1 =20 men

D1 = 52 days

w1 = w

in second condition

M2 =?

D2=60 days

w2 = 3w

from formula m1*D1/w1=M2*D2/w2

20*52/w=M2*60/3w

20*52=20*M2

M2=52

therefore,

more men required

52-20=32 Ans.