20 person can do a work in 180 days then how many person will be required to complete that work in 40 days​

Answers

Answered by chinmay433sahoo
0

Answer:

180 DAYS= 20 PERSON

40 DAYS = ?

THEREFORE IN 40 DAYS  

NO OF PERSON IS 180/20= 9 PERSONS

Step-by-step explanation:

Answered by Anonymous
0

Step-by-step explanation:

20=180 days

So do it for 30 days

we have to times 40 days*4.5

.=180

So it means that they need 180 people to complete he work