21. A and B can separately complete
a piece of work in 20 days and
30 days respectively. They
worked together for some time,
then B left the work. If A com-
pleted the rest of the work in 10
days, then B worked for
(1) 6 days (2) 8 days
(3) 12 days (4) 16 days
without x
please use trick
Answers
Answered by
53
Answer :
Option 1) 6 days
Explanation :
10 days work of A = 10 × 3
=> 10 days work of A = 30 units
Therefore, (60-30) = 30 units of work would have been done by A.
For B,
=> 30/(3+2)
=> 30/5
=> 6 days
Therefore, B worked for 6 days.
Answered by
25
Solutions
according to question:-
A and B can separately complete
A and B can separately completea piece of work in 20 days
Work done by A in 10 days = 10/20 = ½
Days required by (A+B) together to complete ½ work =½ /(1/20 + 1/30)
= 6 days