Math, asked by pranitnexus2759, 1 year ago

24 men can complete a work in 10 days working 8 hrs per day. after 4 days 8 workers left in howmany hours a day men works

Answers

Answered by endless99
1
Given

24 men complete the work in 10 day, if working 8 hours/day.

If working time increase by 2 hours/day.

Then , how many worker need=?

Let after increased 2 hours /day work may complete in 5 days.

M1×D1×H1= M2×D2×H2

M1=M2= Men

D1=D2= Days

H1=H2= Hour

And given data is.

M1= 12.

D1= 5=D2.

H1=8.

H2=10.

M2= ?

12×5×8=M2×10×5

480/50= M2

9.6 = M2

Approx 10 men are need.