24 men working 8 hours a day finish work in 10 days how many men required to finish same work in 6 days working 5 hours per day
Answers
Answered by
0
Answer:
64 men
Step-by-step explanation:
= (24*8*10)/(6*5)
= 4*8*10/5
=4*8*2
= 64