24 men working at 8 hours per day can do a piece of work in 15 days. In how many day
can 20 men working at 9 hours per day can complete the same work?
Answers
Answered by
5
Answer:
16
Step-by-step explanation:
Total Work (in hrs) = No.of men*No.of hours*No.of days
= 24*8*15
Total work will be same.
Now 24*8*15 = 20*9*x
x=16