24 men working at 8 hours per day can do a piece of work in 15 days. In how many days can 20 men working at 9 hours per day can complete the same work?​

Answers

Answered by juhisinghal21ovndbi
1

Answer:

The job takes 24 men x 8 hrs/day x 15 days = 2880 man-hours

Days Required = 2880 man-hours/(20 men x 9 hours/day) = 16 days