Question:

24 people can construct a house in 15 days But the owner would like to finish it in 10 days. How many more workers will be needed?

Given:

24 people can construct it in 15 days

Find the number of people needed to build it in 1 day:

15 days = 24 people

1 day = 24 x 15

1 day = 360 people

Find the number of people needed to build it in 10 days:

1 day = 360 people

10 days = 360 ÷ 10

10 days = 36 people

Find the number of people to add:

Number of people needed to be added = 36 - 24

Number of people needed to be added = 12

(a) They need 12 more workers.

Question:

The price of 50 books is RS. 2000. What would be the price of 30 such books?

Find the price of 1 book:

50 books = Rs 2000

1 book = 2000 ÷ 50

1 book = Rs 40

Find the price of 30 books:

1 book = Rs 40

30 books = 40 x 30

30 books = Rs 1200

Answer: Rs 1200